This news article was originally written in Spanish. It has been automatically translated for your convenience. Reasonable efforts have been made to provide an accurate translation, however, no automated translation is perfect nor is it intended to replace a human translator. The original article in Spanish can be viewed at Electrabel supera sus primeras 100 horas de funcionamiento en su nueva planta de Teruel

Electrabel exceeds their first 100 hours of operation at its new plant in Teruel

28/06/2006

on June 28, 2006

Electrabel signed has recently surpassed the 100 hours of continuous operation and at full load of the plant's combined cycle which is located in the municipality of Castelnou, in the province of Teruel. This is a milestone for the company, since this is the first unit of generation of electricity from the company in Spain.
After a successful test period started last April 10 with the synchronization of the plant to electrical network of Spain, the plant's combined cycle in Castelnou received launched definitive start certificate awarded by the prefectures in Teruel. During the period of testing the two gas turbines, steam turbine as well as all systems of the plant, already demonstrated its absolute reliability.
The plant has a rated power of 800 MW and represents 11.7% of the total capacity installed in Aragon. As fuel use exclusively natural gas and can achieve an annual consumption of up to 1 bcm (billion m3), approximately 3% of the total consumption of gas in Spain per year. Also, the company will sell Castelnou plant energy production to the operator of the electricity market (Omelokovshchina) from the center of management of the energy that Electrabel is in Madrid.
The firm develops other combined cycle projects in Spain, in particular, in Morata de Tajuña (Madrid) with a 1,200 MW plant, and another joint project with the Sniace in Torrelavega (Cantabria) company for the construction of a 800 MW plant.
Combined cycle of Electrabel in Castelnou (Teruel) plant
Combined cycle of Electrabel in Castelnou (Teruel) plant

Suscríbase a nuestra Newsletter - Ver ejemplo

Password

Select all

Autorizo el envío de newsletters y avisos informativos personalizados de interempresas.net

I authorize the sending of communications from third parties via interempresas.net

He leído y acepto el Legal notice y la Data protection policy

Responsable: Interempresas Media, S.L.U. Purpose: Subscription to our newsletter(s). User account management. Sending emails related to the same or related to similar or associated interests.Retention: for the duration of the relationship with you, or as long as necessary to carry out the specified purposesTransfer: Data may be transferred to other group companies for internal management purposes.Rights: Access, rectification, opposition, deletion, portability, limitation of processing and automated decisions: contact our DPD. If you consider that the processing does not comply with the regulations in force, you may lodge a complaint with the AEPD.More information: Data protection policy

REVISTAS

VÍDEOS DESTACADOS

  • Guía de instalación y mantenimiento de Discos de Ruptura

    Guía de instalación y mantenimiento de Discos de Ruptura

TOP PRODUCTS

NEWSLETTERS

  • Newsletter Química

    19/09/2024

  • Newsletter Química

    12/09/2024

Highlighted links

Smagua - Feria de ZaragozaSalón de gas renovableAWA Show2be

Latest news

Featured companies

OPINIÓN

ENTIDADES COLABORADORAS

OTRAS SECCIONES

Services