For three years, Hune supplies electricity to the farm of Insuíña. In total there are five generators in the area of swimming pools, laboratory and offices of the Galician installation. Production of turbot in the town of Xove (Lugo) has access to electricity with five generators of Hune. The Centre has 3 teams of 100 kva for the bombs, 1 500 kva of laboratory and offices in the region and 1 in 200 kva for the lighting of the premises.
The teams operating in pumps 3 x 1000 kva are connected together to add powers. It also has a team to failure, as in the case of incidence, would not be affected the normal operation of the rest of the installation that is dedicated to the supply of seawater to the pools, as a centre of production of turbot.